UK & Ireland Featured Project: Cadent Mineral Blue / isCompliant Implementation (1603)

QEM Solutions have been assisting Cadent Gas with the implementation of our Mineral Blue and isCompliant software. By developing a bespoke connection between the two suites, QEM were able to establish a streamlined process for gathering project milestone achievements. Balancing these achievements with audit and inspection results have enabled Cadent to to get a true measure of project success.

Tell Me More...
Overseas Featured Project: Capita Symonds - Valve Inspections

QEM Solutions were contracted to carry 3rd party inspection and witnessing activities on a series of valves fabricated in Germany for a series of SGN contracts throughout Scotland.

Tell Me More...
We are QEM Solutions We are QEM Solutions

We are problem solvers. We are organisers. From the project start-up to the very final evaluations and analysis, we can bring enthusiasm to each and every part of your project.

 

 
Our projects

Our Projects

Combined, we have over 50 years experience, gained on a variety of projects throughout the world. But no two engineering projects are alike.

Sometimes we manage a project from the very start and continue to be involved until the end reports. Other times we are brought in to provide specialist services in specific areas. Each brings different challenges. Each has different outcomes.

We would like to share just a few of these projects here.

Show map

Our Projects

AMEC - Isle Of Grain Pipeline, AGI's and MOC Design Process Compliance

AMEC Industrial

Isle Of Grain, England
1 Oct 2006 - 1 Oct 2007

AMEC Industrial were awarded a contract to produce the design for the construction of a reinforcement pipeline from the Isle of Grain to Gravesend South AGI, including the installation of pig-trap facilities at Gravesend and the Isle of Grain.

At the Isle of Grain LNG facility, National Grid were to extend the LNG storage capacity of the site by constructing additional LNG storage vessels. This additional stored gas will be vaporised and pressurised and used to supply gas to the UK gas transmission system.

QEM Solutions were contracted to assist the Amec / National Grid Alliance with the development of existing and new design processes in line with CDM and National Grid requirements.

Benefits of engaging QEM Solutions

  • Part-time assistance as and when necessary.
  • Development of industry best practice. 
  • Commitment to "get the job done".

Responsibilities included:

  • Review of current design processes. 
  • Identification of processes required to satisfy MFS and contract. 
  • Identification of processes required to satisfy CDM Regulations 2007. 
  • Development of risk mitigation during design processes. 
  • Development of improvements to AMECs internal safe by design management system. 
  • Creation of project specific documentation. 
  • Identification of project close-out requirements in form of risk registers and other associated documentation.

 Services Breakdown

  Design Process Compliance

 Engaged Specialists