Laing O'Rourke - Wormington to Sapperton Pipeline Design
Design Co-ordination
National Grid, Laing O'Rourke
The Cotswolds, England
8 Jan 2009
-
12 Jan 2010
The project was to revalidate a previous pipeline design from several years previous. The scope included the AGI changes at the Wormington Compressor site, pipeline routing and design to Sapperton AGI. QEM Solutions were managing the multi-disciplinary design team on behalf of Laing O'Rourke.52.014
Benefits of engaging QEM Solutions included:
-
Multi-disciplinary design team management.
-
Extension pipeline and AGI design experience.
-
Drive to complete the design within the clients time constraints.
Main responsibilities:
-
Management of landslide design including sub-contractors on specialist services.
-
Management of the electrical and instrumentation design to National Grid and international specifications.
-
Management of the pipeline design and route changes.
-
Co-ordination of the G17 requirements for the project.
-
Tendering for the materials contract on behalf of the client.
-
Procurement and expediting of the pipeline and AGI materials.
-
Management of QA Activities for the material certification.
-
Managing the delivery of the handover documentation to the clients requirements set out in their NSBP007 specification (now BP007G).
-
Chair at the design meetings.