Rayden Engineering - Authorising Engineer (1421)
Authorising Engineers
Rayden Engineering Ltd
Hebden Bridge
8 Jul 2016
-
31 Jul 2016
QEM SOlutions were engaged by Rayden Engineering s to assist the commercial manager on the Hebden Bridge PIG recovery project.
Responsibilities included:
-
Hold the Permit for Deep excavation and hotworks
-
Supervise the works to ensure it complies with the permit restrictions
-
Co-ordination with NGN and third parties
-
Assistance with the NRO preparation
QEM will provided suitabley trained and competent Consultant in the form of a Competent Person Engineer, with the back-up support from teh QEM head office. Paul was already on the NGN database via QEM Solutions to hold the permit once his SCO and EUSR training is complete, so this enabled a smooth process without any delays to ptoject timescales.