UK & Ireland Featured Project: Weld Inspection & Consultancy United Utilities Thirlmere (1737)

QEM Solutions were asked by United Utilities to assist with the review of the welding process and associated with the provision of the innovative steel E-joint.

Tell Me More...
Overseas Featured Project: Capita Symonds - Valve Inspections

QEM Solutions were contracted to carry 3rd party inspection and witnessing activities on a series of valves fabricated in Germany for a series of SGN contracts throughout Scotland.

Tell Me More...
We are QEM Solutions We are QEM Solutions

We are problem solvers. We are organisers. From the project start-up to the very final evaluations and analysis, we can bring enthusiasm to each and every part of your project.

 

 
Our projects

Our Projects

Combined, we have over 50 years experience, gained on a variety of projects throughout the world. But no two engineering projects are alike.

Sometimes we manage a project from the very start and continue to be involved until the end reports. Other times we are brought in to provide specialist services in specific areas. Each brings different challenges. Each has different outcomes.

We would like to share just a few of these projects here.

Show map

Our Projects

SGN - Flowstop Engineering Vendor Assessment (1736) Vendor Approval, Inspection and Expediting

Scotia Gas Networks (SGN)

Dartford
5 Mar 2019 - 2 Apr 2019

QEM Solutions were asked as our continued commitment to assisting SGN with their Vandor Validation programme to carry out a Vendor Quality Assurance Audit on Flowstop Engineering Ltd (FSL). FEL have been manufacturing a variety of below 7 bar fittings for over a year in their new factory and SGN requested QEM to verify the FEL processes and systems were suitable to be manufactured to relevant GIS Standards (GIS-14525, -C8 & -F13).

The fittings for approval are listed below.

  • Fabricated Flange Adapter 14”thru 48”
  • Fabricated End Cap 14” thru 48”
  • Fabricated Under Pressure Tee 14” thru 48”
  • Fabricated Stopple Tee 14” thru 48”.
  • Fabricated CISBOT Tee 14” thru 48”
  • Fabricated CIRRIS Tee 14” thru 48”

QEM undertook a process audit to ensure the necessary systems are in place to manufacture the fittings in the new factory and sample checked compliance with the specifications provided

 Services Breakdown

  Quality Control and Verification

 Engaged Specialists