NGN - Biomethane Project Management (1400)
Quality Management
Leeds
6 Jul 2015
-
18 Nov 2016
As part of the NGN professional service contract QEM lead the delivery of 5 biomethane connection for the end of March 2016 to meet the renewable heating incentive. The role included for the co-ordination and management with the biomethane producers to ensure they met their obligations to enable them to flow gas in to the gas network. Each of the 5 connections to be completed were different; pressure, producer, type of equipment, installation contractor etc
The team had to ensure that prior to the gas to grid the following was prepared for each connection:
• Network Entry agreement
• Letter of Direction was issued by OFGEM for the connection point
• Produced an approver design in line with G17 Part B for all disciplines
• The installation met the requirements to enable them to be commissioned
• Coordinate the NGN teams for commissioning and end to end testing
• The Written Scheme of Examination were produced and agreed with NGN
• The gas sample for the biogas met the minimum required standard
• The metering to ME2 was completed
The team continues to manage to requests to connect to the NGN gas network and for the next phase of projects.