QEM Solutions were asked to assist MultiTech Contracting in developing their internal design and risk mitigation processes to ensure that they promoted and implemented industry best practice from both a legislative and an engineering / design perspective.
Working with both the Edinburgh and Warrington Offices, QEM identified possible gaps in the design process and offered improvements that could integrate directly with the companies existing policies and procedures.
The result was a process that brought in the reality of fast paced engineering and combined it with industry best practice, ensuring that all risks associated with construction, operation and decommissioning stages were mitigated, where possible, at the design stage.
Working over a 6 month period, QEM established and implemented new processes on both corporate and project levels.
The timely implementation meant that MultiTech could apply the new processes to both the Burnhervie and Girvan pipeline projects for Scotia Gas Networks.